Agile Velocity & Capacity Forecaster

Explore a synthetic planning scenario and export a memo. The sprint history and risk flags are examples, not a real team record. Dates start on August 24, 2026 and count weekdays; holidays are not excluded.

Target confidence

99.3%

by Sprint 6

Sustainable velocity

53 pts

per sprint

P50 completion

S5

Nov 2, 2026

P80 estimate

S6

Nov 16, 2026

P90 risk case

S6

Nov 16, 2026

Monte Carlo completion curve

Cumulative probability of full backlog delivery

10,000 randomized velocity passes

Velocity reliability

12-sprint delivery trend

Reliability: 93%Rolling average = 3 sprints

Value vs. effort

RICE backlog matrix

Prioritization queue

Enterprise RICE backlog

FeatureReachImpactEffortRICEDecision
SSO + SCIM provisioning923549.7Quick Win
Portfolio delivery cockpit883828.1Strategic Bet
AI release-risk assistant7631312.3Strategic Bet
Bulk workflow approvals812348.6Quick Win
Regional data residency543139.3Resource Trap
Legacy report builder38183.1Resource Trap
Slack incident digest662335.2Quick Win
Dark-mode preference321215.2Fill-in

DMAIC anomaly audit

Delivery risk register

Scope Creep

High

+18% unplanned story points in the last three sprints

Define phase

Quality Regression

High

Escaped defects rose above the 2.0 / sprint control limit

Analyze phase

Cycle Time Variance

Medium

P85 cycle time is 1.6× the team baseline

Measure phase

Planning memo

Delivery estimate & example risks

Export the scenario assumptions and completion estimates as Markdown.

# Delivery Planning Scenario

Synthetic history and example risk flags. These estimates are not a delivery commitment.

## Scenario inputs
- **Backlog scope:** 260 story points
- **Delivery team:** 8 engineers at 72% focus factor
- **Sprint cadence:** 10 business days
- **Target milestone:** Sprint 6 (Nov 16, 2026)

## Forecast
- **Expected sustainable velocity:** 53.0 story points / sprint
- **Monte Carlo trials:** 10,000
- **P50 completion:** Sprint 5 (Nov 2, 2026)
- **P80 completion:** Sprint 6 (Nov 16, 2026)
- **P90 completion:** Sprint 6 (Nov 16, 2026)
- **Probability of target:** 99.3%

## Example feature priorities
- **SSO + SCIM provisioning**: Quick Win; RICE 49.7
- **Portfolio delivery cockpit**: Strategic Bet; RICE 28.1
- **AI release-risk assistant**: Strategic Bet; RICE 12.3
- **Bulk workflow approvals**: Quick Win; RICE 48.6
- **Slack incident digest**: Quick Win; RICE 35.2

## Example delivery risks
- **Scope Creep (High)**: +18% unplanned story points in the last three sprints. Control owner: Delivery Lead; DMAIC phase: Define.
- **Quality Regression (High)**: Escaped defects rose above the 2.0 / sprint control limit. Control owner: Delivery Lead; DMAIC phase: Analyze.
- **Cycle Time Variance (Medium)**: P85 cycle time is 1.6× the team baseline. Control owner: Delivery Lead; DMAIC phase: Measure.

## Planning note
Treat Sprint 6 as a scenario estimate. Check the inputs with the delivery team before making a commitment.